Project Details

Project: Remove and Replace Fiber Optic Cable - Flandreau Indian School
Location: Flandreau, SD
Client Name:

Department of Interior; Bureau of Indian Education

Contract Value: $213,684.30
Period of Performance: October 2022

Project Narrative

The project entailed the termination and installation of 12 ct SM fiber. There were 13 IDF locations. LC connectors were used to terminate. New fiber shelves were installed in all locations. Install and terminate to existing data racks. Caple support was added as needed. All cables were tested and certified. This project included all trenching, boring and conduit for data wires. The existing building penetrations were utilized, and handholds and junction boxes were added.